Insights

Spain Creates an Electricity Capacity Market

In Short

The Situation: Following EU State aid clearance of up to €9 billion over 10 years, the Spanish government has approved Ministerial Order TED/966/2026 establishing a capacity market for the peninsular electricity system (the "Order"). The Order introduces a new framework for procuring capacity to support electricity-system adequacy and security of supply.

The Result: The Order establishes a centralised capacity market administered by Red Eléctrica de España, procuring firm capacity ("MW") through sealed-bid, pay-as-bid auctions. Eligible participants include generators, storage operators, final consumers, demand aggregators and aggregators of electricity production and storage. New investments participating in the main auction are limited to renewable generation, storage or demand-side resources. Existing generation installations face an emission-intensity gate of 550 g CO₂/kWh. Contract terms range from 12 months for existing assets to up to 15 years for new investment; demand installations may choose terms of one to 10 years.

Looking Ahead: Following its publication in the Boletín Oficial del Estado on 17 September 2026, the capacity market entered into force on 18 September 2026. Market participants should assess eligibility, emission compliance, firmness coefficients and bidding strategy now―particularly given that transitional auctions are expected to commence shortly after entry into force.

Regulatory Background

In May 2026, the European Commission approved Spain's proposed electricity capacity mechanism, authorising an estimated budget of up to €9 billion over a 10-year period.

Following this approval, Spain's Ministry for the Ecological Transition and Demographic Challenge approved the Ministerial Order TED/966/2026, of 15 September 2026, establishing the Order. The Order entered into force on 18 September 2026 and created Spain's first market-wide capacity mechanism: a peninsular centralised capacity market open to generation, storage and demand-side resources, structured around sealed-bid, pay-as-bid auctions.

How the Spanish Capacity Market Works

General framework. The Order establishes a centralised capacity market (as distinct from a strategic reserve). The procured product is firm capacity in MW. The offer variable is the price per MW of firm capacity per year (€/MW/year, no decimals).

Settlement is sealed-bid, pay-as-bid: each successful bidder is paid its own bid price, not the marginal clearing price. This contrasts with the pay-as-cleared mechanisms used in Great Britain, Italy and France; Belgium is the principal European precedent for a pay-as-bid capacity mechanism.

The firm capacity is procured through competitive auctions. The Order creates two auction modalities, together with a transitional auction regime:

  • Main auctions: procure the system's firm-capacity needs. Delivery starts within a maximum of five years from award (or up to nine years for qualifying new investments allocated to a specific investment quota). Contract duration varies by technology:

Spain electricity capacity market contract durations: 12 months for existing generation and storage, up to 15 years for new investments, 1–10 years for demand installations, and 1 year for production and storage aggregation.

In addition to a possible confidential maximum price cap on the required-firm-capacity curve, a confidential lower reserve price may be set for existing installations other than demand. However, existing generation or storage installations planning a new investment may request that it not apply. 

  • Adjustment auctions: annual, with 12-month delivery starting within 12 months of award. Only installations already in service may participate. Designed to resolve unforeseen or residual adequacy gaps.
  • Transitional auctions: held from entry into force of the Order until the first main-auction delivery period begins. One per calendar year, annual delivery.

Institutional architecture. The administrator of the market is Red Eléctrica de España, S.A., acting as system operator and auction administrator. The supervisor is Comisión Nacional de los Mercados y la Competencia, as auction supervisor, validating objectivity, transparency, non-discrimination and competitiveness of each auction. The convening authority for auctions is the Secretaría de Estado de Energía, although results are resolved by the Dirección General de Política Energética y Minas.

Eligibility requirements. The market is open to: (i) electricity producers; (ii) storage owners; (iii) final consumers; (iv) demand-aggregation providers (including suppliers); and (v) aggregators of electricity production and storage. Offer blocks must be at least 1 MW of firm capacity.

Firmness coefficients (ranging from 0 to 1) are applied to installed capacity to derive firm capacity. These perform a function broadly analogous to the de-rating factors used in other capacity markets. Only technologies with a defined firmness coefficient can participate.

Additionally, new investments participating in the main auction are limited to renewable generation, storage and demand-side resources, reflecting the mechanism's decarbonisation orientation; whereas existing generation installations must satisfy a maximum emissions intensity of 550 g CO₂/kWh.

Existing non-renewable generation must additionally meet a flexibility-coefficient threshold―the ratio of energy mobilised through manual-activation balancing markets to energy produced―set by reference technology in each auction call.

Remuneration. Successful bidders receive a fixed monthly payment equal to (1/12) × awarded firm capacity (MW) × award price (€/MW firm/year). Payments commence from the start of the delivery period, settled monthly. The award price and awarded capacity are not indexed or updated.

Competition safeguards. Each auction call may also set a minimum ratio of bids received to the firm capacity procured and a maximum share of total awarded firm capacity attributable to any single company or corporate group.

Environmental criterion. Exceptionally, a main-auction call may set a maximum emissions threshold that awardees may not exceed. To that end, CO₂-equivalent emission levels may be defined for each emitting reference technology so that, taken together, the CO₂ emissions of the successful installations remain below that threshold. In the selection of offers, bids from the highest-priced emitting technologies that would cause the threshold to be exceeded are discarded. For hybrid installations, the CO₂-equivalent emission level is the average of each participating module's emissions, weighted by its firm capacity.

Testing. Availability may be tested at least annually, with up to three successive tests: a first failure costs one month’s remuneration plus 20%, a second costs a quarter’s remuneration plus 20%, and a third costs the annual remuneration plus 20% and disqualifies the installation. Additionally, failure to comply with the obligation to provide firm capacity when required may lead to payment obligations.

Financing. The annual cost of the mechanism is funded by electricity suppliers, including suppliers of last resort, and by consumers purchasing directly in the wholesale market, through unit prices comprising an energy term, differentiated by tariff segment and time period.

Secondary market. The Order contemplates a secondary market to enhance liquidity: capacity rights and obligations may be ceded or transferred to third parties, subject to prior approval to verify that the transferee meets all eligibility requirements. The transfer must be requested at least two months before the first affected calendar year, and must comprise all the firm capacity awarded to the transferor for a natural year. This does not preclude participation in later auctions.

Cross-border participation. Installations in zones bordering Spain may participate once TSO coordination agreements and compliance conditions are approved.

Next steps. The Secretary of State for Energy must approve by resolution the operating procedure for the capacity service (covering technical, documentary and operational requirements, qualification, provider obligations, verification and testing, settlement, etc.) as well as the auction call.

How Spain Compares: European Capacity Markets

All European capacity mechanisms share a common regulatory backbone: EU State aid rules and the capacity-mechanism provisions of Chapter IV of Regulation (EU) 2019/943. Most are centralised, TSO-administered schemes. However, Spain's design incorporates distinctive features that differentiate it from the models prevalent elsewhere―notably pay-as-bid settlement and a multi-track (main, adjustment and transitional) auction structure.

Spain's choice of pay-as-bid settlement is relatively uncommon in Europe. Belgium is the principal European precedent for the pay-as-bid model. The Great Britain, Italy and reformed French mechanism use pay-as-cleared pricing, which is generally considered to promote price discovery and reduce strategic bidding. Under Spain's pay-as-bid design, each successful bidder receives its own bid price rather than a uniform marginal clearing price.

Also, Spain's design goes beyond the minimum EU emissions framework in two respects. First, existing generation must comply with a standalone 550 g CO₂/kWh emissions-intensity ceiling. Second, new investments participating in main auctions are restricted to renewable generation, storage and demand-side resources. Together, these requirements give the Spanish mechanism a comparatively strong decarbonisation orientation.

Three Key Takeaways

  1. Assess eligibility now. Existing fossil plant operators should confirm whether their installations meet the 550 g CO₂/kWh threshold and the flexibility-coefficient threshold to be set in each auction call. These are likely to be among the key gating factors for existing non-renewable generation. On the other hand, storage and demand-side response technologies are explicitly favoured for new building in the main auction. Early action on metering, verification and manual-activation balancing-unit qualification will be essential. The same applies to firmness coefficients, as de-rating factors will be decisive for storage and variable technologies.
  2. Map assets to the right auction track and monitor the first auction calls. Main auctions—with a longer forward procurement horizon and potentially multiyear commitments for qualifying new investment and demand resources—and adjustment auctions—with a short procurement horizon and 12-month delivery—carry materially different commitment and revenue profiles and should be factored into project financing and bidding strategies. Additionally, transitional auctions are expected first.
  3. Do not assume cross-market transferability. Group-level EU operators with portfolios across multiple capacity markets (Great Britain, France, Italy, Belgium) should not assume that their existing bidding strategies or eligibility assessments transfer to Spain. For operators coming from pay-as-cleared markets, the pay-as-bid settlement mechanism alone requires a fundamentally different approach to bid formulation. Bidding strategy, contract-term planning and emission-eligibility assessments do not transfer directly between jurisdictions. Spain's model requires independent commercial and regulatory analysis.
Insights by Jones Day should not be construed as legal advice on any specific facts or circumstances. The contents are intended for general information purposes only and may not be quoted or referred to in any other publication or proceeding without the prior written consent of the Firm, to be given or withheld at our discretion. To request permission to reprint or reuse any of our Insights, please use our “Contact Us” form, which can be found on our website at www.jonesday.com. This Insight is not intended to create, and neither publication nor receipt of it constitutes, an attorney-client relationship. The views set forth herein are the personal views of the authors and do not necessarily reflect those of the Firm.